Project Background
Project: Interlock Pavement
Main Contractor: Fikile Construction
Location: Cnr. Caversham and, Hagart Rd, Pinetown
Square Metres
G-Block Concrete
80 mm Pavers
mm
Kerbing
m
saw cut
Edging
Pre-construction
Dson Industries were excited and privileged to be invited to bid for the external works .Initially we were asked to provide rates in pre-calculated B.O.Q based purely on a ‘supply fit’ basis. Having mentioned the Dson Industry installation capabilities during an early meeting, we were subsequently awarded the job.
Working at height
With the Retaining Wall 4.5 meters in height next , this required health and safety precautions to allow for safe working of the installation team.
Ahead of Schedule
Dson originally quoted 14 days to install the pavement. We would need to work hard to ensure we met the timings set out in the schedule of works, however our experience in managing personnel and our understanding of the logistics involved in delivering and handling large volumes of materials, meant that we were confident we could meet (and on this project exceed) the stated completion date. In fact Dson Industries were able to complete
installation in 6 days.
Dson Industries
Ground Floor – Building 2
Gleneagles Park
10 Flanders Drive
Mount Edgecombe
073 557 1040
info@dsonindustries.co.za
Office Hours
Mo-Fr: 8:00-17:00
Sa: 8:00-14:00
So: closed
Categories
Latest Projects
Kloof Giant Within Giant-Within Integrated HealthJanuary 23, 2021 - 1:36 pm
Redefine Dental 165 Rinaldo Road Glen Hills Durban NorthDecember 7, 2020 - 3:22 am
Architectural Gabion 6 Conway Rd WestvilleDecember 6, 2020 - 8:19 am
78A Beechgate Crescent SouthGate Business Park.September 17, 2020 - 9:13 pm
erf 962 Kingsburgh Storm Water ChannelSeptember 12, 2020 - 2:23 pm