Integrity
From the company’s inception, integrity has been at the heart of the way we conduct business. We lead by communicating openly and are fully accountable for our actions.
East Rand Junction (ERJ) has been investing in the area including this R40m site development.
As part of a planned development of Kingsburgh Commercial and Industrial Park site (an area of approx. 65 000m2) that would be for:
Site comprises upper and lower level platform areas, with internal access roads, pedestrian access and connecting walkways to the proposed buildings.
On 17 June 2017 a slope failure took place on Section number 8 situated next to the conservation area. Slope had been constructed at 1: 1 with a height of 32m from the toe. The filled slope composed predominantly of instu fill. First attempts toward stabilisation called for reducing the driving forces by flattening the slope to 3: 1. Although stability analyses based on the assumption that the water table was at the ground surface predicted a safe condition, the regraded slope remained stable only until the following big storm of October 2017, when a second much larger slide occurred. It was obvious that a close relation existed between rainfall intensity and slope movement. Also, calculations in stability studies indicated that the average soil shear strength was much lower than originally assumed.
Reduce Driving Forces and Restrain Landslide Mass
Since the driving forces were essentially gravitational because of the weight of the soil and water and the fact that stability of soil slopes is a limiting equilibrium problem in which the external forces acting on a soil mass are at least balanced, the design to stabilise the slope had to address ways to ensure proper safety from the forces tending to cause movements. Analysis had to be performed for anticipated loadings as well as structural capability to restrain landslide mass.
tons of earth works.
Litres of
Diesel
2 by 1 by 1
Gabion Baskets
Gabion Rocks
Geotextile
Exposed ground after excavations did offer solid base for a loading bearing. Dson Industries Syncline Geotechnical Engineering Pty (Ltd) to conduct a Geotechnical Investigation for the “Proposed Gabion Retaining Wall at Kingsburgh Industrial Park (Uitsig Road, Astra Park), eThekwini Municipality”.
Foundations for Lateral Support System
Due to the presence of potentially collapsible sandy fill soils and underlying potentially compressible alluvial clays at anticipated founding level, it was
recommended that some ground improvement be carried out prior to foundations of the retaining wall (as per below):
ERJ were keen to explore a gabion retaining wall solution for the
project. Dson Industries were initially approached by developer Len Brown of East Rand Junction to facilitate an effective, practical solution to address the slope mass instability difference in levels throughout the site.
In the early stages of the project planning phase, there were a number
of meetings , both on-site and at the client’s offices. This was an important part of the planning approval process.
Meetings between the companies and the architects prior to construction, resulted in Dson Industries being asked to design, supply and install a 6m high Mass Gravity Gabion Retaining Wall and a mass gravity reinforced earthworks slope retaining system.
Dson Industries were contacted in October 2017 to consult on the Project. It was a further 10 months before we were able to commence works (whilst the main site contractors completed the initial construction phases).The intervening period was certainly useful in terms of project planning and ongoing consultation
Dson Industries were contacted in October 2017 to consult on the Project. It was a further 10 months before we were able to commence works (whilst the main site contractors completed the initial construction phases).
The intervening period was certainly useful in terms of project planning and ongoing consultation
Site Conditions presented considerable complications for material handling and safe working conditions. Bulk materials would be offloaded at top level platform and the Gabion structure being constructed located 30m below. Two driveways were cut across the steep banks to facilitate material conveying.
Design engineer consultations
• Production of as-built drawings
• Supply of Galvanised Gabion baskets in line with the design and
supply to site
• Technical and engineering support
• Supply and installation of geotextile membrane
• Drain Pipes
• Mass gravity gabion retaining wall installation including hand-placed facing stones
| THE PROJECT: | Section 8 Development Works |
| APPLICATION: | Mass Gravity Retaining Wall |
| LOCATION: | ERF 962 Kingsburgh |
| DATE: | July 2018 |
| CLIENT: | East Rand Junction (ERJ) Len Brown |
| ARCHITECT: | Architectural Concepts Barry Liggins. |
| GEOTECHNICAL ENGINEER | Syncline Geotechnical Engineering (Pty) Ltd |
| Pr. STRUCTURAL ENGINEER | Mani Govender |
From the company’s inception, integrity has been at the heart of the way we conduct business. We lead by communicating openly and are fully accountable for our actions.
In providing our Project Management and Consulting Services in Durban and South Africa at large, we rely upon an archived understanding for having been there a thousand times before and we make each and every client the beneficiary of these time tested experiences.
How we differ from others is measured not in a costs for the performance but, in the value in knowing you can delegate such responsibilities to someone that will get it done correctly…first time,…every time!
It is our belief that in projecting our competence for our craft we must first gain your confidence and respect for what that difference can mean. The differences between us and other firms isn’t price, its passion driven familiarity!
Through formal or informal design assist relationships, we work together with owners, architects, engineers, and subcontractors from the early stages of pre-construction in order to brainstorm and research design options, review for construct-ability, and analyze cost implications.
Thoroughly managing the construction process is vital to completing projects on time, under budget, and to the clients’ satisfaction. Dson Industries’ project management staff and field leadership collaborate to rigorously plan and regularly update each project’s costs and schedule, maintaining close control of the job and taking advantage of efficiencies wherever possible.
Ground Floor – Building 2
Gleneagles Park
10 Flanders Drive
Mount Edgecombe
073 557 1040
info@dsonindustries.co.za
Mo-Fr: 8:00-17:00
Sa: 8:00-14:00
So: closed
erf 962 Kingsburgh Storm Water Channel 